A typical Kitchen Remodel starts with demo of existing finishes for a new layout with cabinets, countertops, fixtures, lighting, floors, drywall, paint, and appliance installation. After our budget is established, we order the cabinets (usually 5 week lead time), and during this time we procure all the material, so that demo can start a few days before cabinet installation. A total Kitchen Renovation from contract to finish is usually 8 weeks, but keeping your house relevant in today's real estate market is a must to preserve your home investment.